Client: Berkeley Group
Type: Residential
Location: London
Status: Live
Service: Hoists
- Delivery a seven Hoist scheme
- 517 new home development
Case Study
Vertical logistics strategy, delivering a seven Hoist scheme for phases two and three of the 517 new home development.
This complex project required expert consultation to overcome the three different slab-level orientations. Select devised a common tower solution to interface from the main structure back to the hoist facade.
On a 37-storey building a two-hoist scheme is very tight, so Select provided a SCANDO 650XL combination machine. These machines offer a payload of 3200kg and operate up to 100 metres per minute.
Click here for more information on how the Hoist team delivered this project
“The Select team provided us with an absolutely fantastic Hoist strategy. This allowed our various contractors to be in charge of their complete delivery management. We've been able to completely eliminate the need for telehandlers across the projects.”